Use this checklist before putting a database into production: backups, users, security, config, monitoring, and restore test. Ensures nothing is missed and the database is ready for production load and recovery.
Intent: Checklist
Quick answer
- Backups: backup job scheduled and successful; retention configured; restore test passed. Users: least-privilege users for each app; no default passwords; credentials in vault.
- Security: bind to private IP; firewall and pg_hba or user host restricted; TLS for connections. Config: memory and connection limits tuned; logging appropriate for prod.
- Monitoring: health check (connect and simple query); disk and connection metrics; backup success alert. Runbook: restore and failover steps documented and tested.
Prerequisites
Steps
-
Backups and restore
Backup schedule and retention confirmed; last backup successful; restore test passed. Off-site or second-region copy if required.
-
Users and security
Dedicated users per app with minimal privileges; passwords in vault. Network restricted; TLS enabled; audit or logging enabled as required.
-
Config and capacity
Memory and connection parameters tuned; max_connections and pool size aligned. Disk space and growth monitored; no test or default databases exposed.
-
Monitoring and runbook
Health check and metrics (connections, disk, replication lag); alerts on failure and capacity. Restore and failover runbook documented and tested; on-call knows how to use it.
Summary
Checklist for backups, users, security, config, monitoring, and runbook before production. Use this so the database is ready for go-live and recovery.
Prerequisites
Steps
Step 1: Backups and restore
Confirm backup schedule, retention, and a successful restore test.
Step 2: Users and security
Least-privilege users; credentials in vault; network and TLS locked down.
Step 3: Config and capacity
Parameters tuned; connections and disk monitored; no test DBs in use.
Step 4: Monitoring and runbook
Health and metrics; alerts; restore and failover runbook tested and known.
Verification
- All checklist items complete; database is ready for production and recovery.
Troubleshooting
Missing backup — Set up and verify before go-live. Restore not tested — Run restore test and document; do not skip.